← Back to 3D Project Tours

Biotech Park, Odisha — Schematic 3D

Client Sapigen Biologix Pvt. Ltd. · PEB Contractor Maxx Infra EPC Solutions
Drawing PD-02 — Column Location Plan · Rev 00 · Issued for Approval · 21.07.26
Steel grid 112.724 × 103.250 m · RCC 113.474 × 104.000 m · Units: metres
Offer ref R0 · 15.07.26PEB ht. 10.8 m · on existing +19 m civil baseWind: 50 m/s · Cat III · k4 1.15

Layers

Sun · 10:30 IST

Section cut

Legend

Grid lines & bubbles
Columns 450□ (to +5.48)
Tapered I frames — A·E·J·P·U
Mezz slab +5.480 (t=150)
Roof / wall sheeting (translucent)
Ridge · eave lines
RCC boundary
Solar panels (seam-clamped)
Fascia band 1.5 m (client-confirmed)
Stair / mumty headroom zones
Uplift — corners −5.7 kN/m²
Uplift — edges −4.4 kN/m²
Uplift — general −3.3 kN/m²
PEB scope: new steel superstructure, clear building height 10.8 m, to be erected atop the client's existing +19 m civil / precast structure (civil works below 19 m are outside PEB scope). All heights below are measured from that +19 m base unless noted as AGL.

What-if simulator — speed & height

33 (zone 1)50 (Bhubaneswar)70
0 (on ground)19 (as built)40
Output (recomputed live)Value
Eave / ridge height AGL
k2 at ridge (Cat III)
Vz at ridge
qz at ridge
Uplift — general roof
Uplift — edge strips
Uplift — corners
Corner purlin line load @1.5 m
Total roof uplift
vs design basis (50 m/s · 19 m)
Exploratory only — Cpe/Cpi, geometry and k1·k3·k4 held constant; uplift scales with qz. The 3D uplift-zone labels and shading update with the sliders.

Site & basis — Bhubaneswar, Odisha

ParameterValue
LocationBhubaneswar, Odisha — cyclone-affected coastal region (Bay of Bengal)
CodeIS 875 (Part 3) : 2015
Basic wind speed Vb50 m/s (wind-zone map; matches confirmed design basis)
TerrainCategory III (client-confirmed)
k1 · k31.00 (general industrial, 50-yr life) · 1.00 (flat)
k4 (cyclonic importance)1.15 — industrial structure, client-confirmed
Cpi± 0.5 (client-confirmed)
Kd1.00 — no directionality reduction permitted in cyclonic region
Height datumsPEB on +19 m base → eave ≈ 29.8 m, ridge ≈ 35.4 m above ground

Design wind pressure vs height

Vz = Vb·k1·k2·k3·k4  ·  pz = 0.6 Vz²  (k2 per Table 2, Cat III)
Height AGLk2Vz (m/s)pz (kN/m²)
10 m0.9152.31.64
15 m0.9755.81.87
20 m1.0158.12.02
29.8 m — PEB eave1.0660.92.22
35.4 m — ridge1.0861.92.30

Roof uplift — net design suction

θ ≈ 5.7° (1:10) · h/w ≈ 0.29 (≤ 0.5) · qz = 2.30 kN/m² at ridge · net = (Cpe − Cpi)·qz with Cpi = +0.5 governing uplift
ZoneCpeNet coeff.UpliftPurlin @1.5 m
General roof (windward slope)−0.94−1.44−3.31 kN/m²−5.0 kN/m
Edge strips (y ≈ 15.5 m)−1.40−1.90−4.36 kN/m²−6.5 kN/m
Corner zones (y × y)−2.00−2.50−5.74 kN/m²−8.6 kN/m
  • Leeward slope Cpe −0.4; wind parallel to ridge ≈ −0.8 / −0.6 — windward-slope + Cpi(+0.5) case governs.
  • Edge-zone width y = lesser of 0.15w and h = ≈15.5 m (0.15 × 103.25 m).
  • Order of magnitude: general uplift over the 11,667 sqm roof ≈ 38–39 MN (≈ 3,900 t) — several times the ~1,200 MT design steel weight.

What this means for the structure

  • Uplift dwarfs roof dead load (~0.25 kN/m²) — clip, purlin and anchor tension capacity governs, not gravity.
  • Seamless clip-fix standing-seam sheeting must be certified for edge/corner suction (−4.4 to −5.7 kN/m²).
  • 49,625 shear studs + 1,160 Hilti chemical anchors carry net tension/shear at the deck and RCC interfaces.
  • Solar load is "additional" for gravity design but cannot be relied on to resist uplift (panels may be absent).
  • Tension-only cross-rod bracing (4 braced bays) transfers lateral wind shear to the +19 m base.
Schematic analysis for review — coefficients interpolated from IS 875-3 tables; Ka/Kc area-averaging & combination reductions apply member-by-member. The STAAD.Pro V22 model (offer basis) governs final design.

Project programme — ~29 weeks

Ref MXI/SBPL/2026-27/001 · R0 · 15 July 2026 — indicative. Click a bar to jump the 3D view to that week; use the ▶ scrubber at the bottom of the screen to build the structure week by week (4D).
Maxxinfra activity Parallel-running Client scope Joint activity

Key site-readiness conditions

  • Civil works ready for anchor-bolt casting; levelled, compacted surface handed over per schedule.
  • 20 m clear space all around the building for crane & vehicle movement; no HT line above the erection area; no deep excavation nearby.
  • Power & water by client; separate labour-hutment area.
  • Fabrication, dispatches and erection hold to schedule only if payments follow PO terms (GA-approval & stage payments on the dates shown).
  • Clear weather assumed; government / festival holidays applicable.
Timeline from "Maxxinfra-Project-Timeline-Sapigen.xlsx". The 4D mapping distributes erection (Wk 6–24) across columns → frames → purlins → deck → slab, then sheeting Wk 25–28 — indicative sequencing, not a method statement.
Schematic visualization from PD-02 + client brief + Revised BOQ — not for construction.

Complete
🖱 Click a column, rafter, roof, mezzanine, wall or uplift zone for design details