MAXXINFRA EPC Solutions
Get a Quote Contact Us
Planning benchmarks from delivered work

How much steel will my building need? Tonnage benchmarks

Delivered structural-steel intensity from MAXXINFRA projects — 55.7 to 161.1 kg/m² across curved-roof sheds, crane buildings and multi-level frames — and planning benchmarks by span, eave height, crane duty and wind zone.

Delivered reference points

Actual all-in structural steel (frames, secondaries, bracing, sheeting, bolts) from MAXXINFRA jobs in Maharashtra, 2022–2025. Wind zone 44 m/s, terrain category 2.

ProjectConfigurationSpanEave / heightCraneBuilt areaSteelkg/m²
Konsari multi-span PEB complexLean-to + 3 multi-gable sheds, 150 m long, 20 bays @ 7.5 m, 4 roof monitors, 180 skylights, cross bracing8 + 3 × 35 m7.0 m (17.3 m end)25 + 10 MT EOT17,289 m²1,406 MT81.3
Chandrapur curved-roof building ACurved MS-1 frame, tube bracing, open end wallsup to 93.8 m—None17,414 m²1,052 MT60.4
Chandrapur curved-roof building BCurved MS-1 frame, tube bracingup to 93.8 m—None25,224 m²1,405 MT55.7
Chandrapur curved-roof building CCurved clear span, rod bracingup to 93.8 m—None5,519 m²350 MT63.4
Konsari helicopter hangarClear-span arch, full-width door opening24.7 m—5 MT2,331 m²160 MT68.8
Konsari expansion shedMulti-gable with crane, 150 m long, expandable end wall, 40 skylights25 m—10 MT EOT, 22 m span3,684 m²272.5 MT74.0
Kaliammal hospital, G+1 frameG+1 steel frame + two-level mezzanine, deck sheet, PU panel roof, brick infill16.4 / 28.7 m9.0 m clear floorNone1,665 m² incl. mezzanine300 MTup to 161

Konsari complex weight breakdown (1,405.7 MT): primary frames 627.5 · crane & jack beams 125.7 · secondary 249.0 · cold-formed 95.0 · walkways 74.0 · roof sheeting 79.2 · roof monitors 51.0 · wall sheeting 33.5 · bolts & anchors 35.7 · louvers & misc 34.1. Design wind 44 m/s, k2 = 1.07.

Planning benchmarks — all-in kg/m² by span and crane duty

Single-storey industrial buildings, 8 m eave, bay spacing 7.5–8 m, 44 m/s wind, terrain category 2, seismic zone II–III. Includes primary + secondary + bracing + anchor bolts + ~6–8 kg/m² sheeting allowance. Apply the adjustment factors below for your site. ±15 % at concept stage.

Clear span (m)NoneUp to 5 MT10 MT20–25 MT
2038–4648–5856–6870–85
2540–4852–6260–7274–90
3042–5254–6562–7578–95
3545–5557–6865–7880–98
4048–6060–7268–8285–105
5055–6868–8076–9295–115
6062–7676–9085–100—
90–95 curved arch55–65———

Values in kg/m² of built-up area. Crane columns apply to the crane-served area; price the rest of the building from the “None” column. 60 m spans with 20–25 MT cranes and curved arches with cranes are engineered case by case.

Free download

Get the benchmark sheet as Excel + PDF

The Excel workbook has the delivered reference points, the full span × crane matrix, the adjustment factors and a worked calculator sheet where you enter area, span, eave, crane and wind zone to get a tonnage range. We email it immediately and give you a direct download link.

  • Sheet 1 — delivered projects with weight breakdowns
  • Sheet 2 — span × crane benchmark matrix
  • Sheet 3 — adjustment factors (eave, wind, seismic, monitors, mezzanines)
  • Sheet 4 — tonnage calculator with formulas

Adjustment factors

VariableAdjustment to the benchmarkWhy
Eave height+3 % per metre above 8 m; −2 % per metre below 8 m (down to 6 m)Taller columns, more girts, larger wind moments
Basic wind speed33 m/s −8 % · 39 m/s −4 % · 44 m/s 0 · 47 m/s +4 % · 50 m/s +9 % · 55 m/s +16 %Pressure ∝ V²; secondaries and bracing respond directly, frames partly — see the wind & seismic lookup
Terrain categoryCat 1 +4 % · Cat 2 0 · Cat 3 −5 % · Cat 4 −10 %k2 changes design pressure at the same wind zone
Seismic zoneZone II–III 0 · Zone IV +2–4 % · Zone V +4–7 %Bracing, connections and crane/mezzanine combinations; more if the building carries heavy mass
Bay spacing6 m −3 % · 7.5–8 m 0 · 9–10 m +4 % · 12 m +8 %Longer purlins and girts; fewer but heavier frames
Roof monitors / ventilators+3–4 kg/m² of building areaMonitor framing, curbs and supports (Konsari: 51 MT on 17,289 m²)
Mezzanine floors+90–130 kg/m² of mezzanine area (beams, joists, deck sheet; excluding slab)Floor live loads of 5–10 kN/m² dominate
Multi-storey steel frame (G+1, G+2)115–160 kg/m² of floor areaComposite floors, moment frames, stairs — Kaliammal hospital 300 MT on 1,665 m²
Large wall openings / open end walls+2–5 %Internal pressure coefficient rises to ±0.7 under IS 875-3 (Chandrapur open-end sheds)
Multi-span sharing columns−4–8 % versus the same spans as separate buildingsShared interior columns and bracing lines

How to use the benchmarks

  1. Pick the span row and crane column closest to your building and take the mid value of the range.
  2. Apply the eave, wind, terrain, seismic and bay-spacing adjustments in sequence (they multiply).
  3. Add roof monitors, mezzanines and large-opening allowances as absolute kg/m² on the affected area.
  4. Multiply by built-up area to get tonnage; carry ±15 % into the budget until a frame design exists.
  5. For cost, apply your current fabricated-and-erected rate per MT, or use the PEB vs RCC calculator which does this with editable rates.

Worked example: a 6,000 m² warehouse, 30 m span, 10 m eave, 10 MT crane across half the floor, at Chennai (50 m/s, zone III, category 2). Benchmark 30 m / 10 MT = 62–75 → mid 68 on the crane half, 30 m / none = 42–52 → mid 47 on the rest. Eave +6 %, wind +9 % → crane half 68 × 1.06 × 1.09 = 78.6 kg/m², rest 47 × 1.06 × 1.09 = 54.3 kg/m². Tonnage ≈ 3,000 × 78.6 + 3,000 × 54.3 = 399 MT, range 340–460 MT.

Frequently asked questions

What is a typical steel weight per square metre for a PEB warehouse?

For a clear-span warehouse of 25–35 m width with an 8 m eave, no crane and a 44 m/s wind zone, MAXXINFRA planning benchmarks run 40–55 kg/m² including primary frames, secondary members, bracing and a sheeting allowance. Light logistics sheds built to minimum specification can be lower; heavy industrial practice with built-up Gr-50 sections, roof monitors and crane provisions is higher.

How much steel does an EOT crane add?

A 5 MT crane adds roughly 10–14 kg/m² over the crane-served area, a 10 MT crane 18–24 kg/m², and a 25 MT crane 32–45 kg/m² — covering crane beams, brackets, stiffer columns and the bracing that carries surge loads. Our 17,289 m² Konsari complex with 25 + 10 MT cranes was delivered at 81.3 kg/m² all-in.

Why can a 93.8 m clear span be lighter per square metre than a 25 m crane shed?

Curved arch-truss roofs carry load mainly in compression and spread the frame weight over a very large floor area, while a small crane shed concentrates crane beams, heavy columns and end-wall bracing on a few thousand square metres. The three curved raw-material sheds we delivered at Chandrapur came in at 55.7–63.4 kg/m² despite the 93.8 m span.

Does the benchmark include sheeting, foundations and flooring?

The benchmarks include primary frames, secondary members (purlins, girts, cold-formed sections), bracing, anchor bolts and an allowance of about 6–8 kg/m² for roof and wall sheeting. They exclude foundations, flooring, mezzanine deck slabs, cranes themselves and architectural finishes.

How accurate are the planning benchmarks?

Treat them as ±15 % at concept stage. Bay spacing, roof slope, openings, mezzanines, monitors, cladding type and the exact IS 875 / IS 1893 parameters move the result. A preliminary frame design, which we provide free within 24–48 hours, narrows it to ±5 %.

More engineering tools

Wind & seismic lookup by city or PIN · PEB vs RCC comparison calculator · Quick steel estimate · 3D project estimator · Crane loads in PEB — FAQ

MAXXINFRA · maxxinfra.in/tools/steel-tonnage-benchmarks/ · planning information, not a design document · © 2026 MAXXINFRA

Want tonnage for your actual building?

Send drawings or a brief — we return a frame scheme and tonnage within 24–48 hours.

Get a Quote Free Consultation